Please report any further instances to the DIO Brunei WSM:
WO1 David Passarelli RE MAPM
Works Services Manager & Works Contracts Officer
DIO (Brunei)
Email: David.Passarelli572@mod.gov.uk
Your cooperation with the above request is greatly appreciated
Hornbill School Access Road Work commence announcement
Pleased be informed that construction works will be carried out in the vicinity of H16 Spg 121.
Scope of works
- Excavation and removal of existing road surface in front of house H16/42A&B, 43A&B,89A&B and 88A&B as indicated in Figure 1 below.
- Extension of laybys
Figure 1
Work Schedule
- Mobilisation Works: Commencing on 1st July 2026
- Excavation commencing on 16th July 2026
Expected Disruptions During Construction
1. Road Access Disruptions
- Temporary road closures and traffic diversions will be implemented
- Access to certain areas may be restricted during excavation and road works
2. Noise disturbance
- Residence in the surrounding area may experience increase noise levels due to hacking, excavation, and other construction activities.
3. Heavy machineries operation
- Loading and unloading of materials will be carried out periodically throughout the construction period.
4. Temporary parking and pedestrian access
- Temporary parking spaces and pedestrian walkways will be designated and made available for residents of the affected houses.
5. Safety measures
- Safety barricades, warning signs, and directional signage will be installed around the work area throughout the construction period.
Apologies for any inconvenience caused and appreciate your patience as these improvement works are carried out.
We appreciate your understanding. For any enquiries, please reach out to the DIO(B) Helpdesk.
Phone Number: 3224130 or military ext 3375
Email: BRUNEIGAR-DIO-HelpDesk@mod.gov.uk or DIORDOSTrg-BruHelpdesk@mod.uk
DIO(B) SCHEDULED WATER TEMPERATURE MONITORING AND CHLORINE TESTING.
1. In Order to Comply with the UK standard, DIO contractor Marsee will be carrying out the scope of works as shown below:
a. Check temperature reading of hot and cold water at the very sentinal point.
b. Check chlorine level in water using site test kit.
c. Visual check and small adjustment of water heater.
d. To record water analysis
e. Duration of work will take 10mins to 15mins.
DIO Scheduled Work
DIO contractors will be carrying out inspection works as shown in the table below. Utilities may be affected during the work, but DIO contractors will try to minimise disruption.
To reschedule, please kindly contact DIO(B) Helpdesk either via phone Calls Ext.3375 or 3224130 or Email: BRUNEIGAR-DIO-HelpDesk@mod.gov.uk during office hours.
DIO contractors will be carrying out inspection works as shown in the table below. Utilities may be affected during the work, but DIO contractors will try to minimise disruption.
To reschedule, please kindly contact DIO(B) Helpdesk either via phone Calls Ext.3375 or 3224130 or Email: BRUNEIGAR-DIO-HelpDesk@mod.gov.uk during office hours.
Planned renovation works at H16 Building 1, 2, 7, and 8
As per agreed renovation or refurbishment programme, DIO(B) contractor will start work at H16 Building 1, 2, 7, and 8 for 6 month from next week for the mobilisation works.
For safety reason, please avoid entering and parking surround the construction site at all times. During working hours, the surrounding area may experience increased noise level, loading and unloading activities, and restricted access due to safety measures. All road access to PCMS, accommodation areas, and the thrift shop will remain available. However, all road users are advised to exercise caution at all times when using these routes.
If you have any concerns or issues related to the works, including health and safety matters, please contact the DIO(B) Helpdesk as you first point of contact.
As per agreed renovation or refurbishment programme, DIO(B) contractor will start work at H16 Building 1, 2, 7, and 8 for 6 month from next week for the mobilisation works.
For safety reason, please avoid entering and parking surround the construction site at all times. During working hours, the surrounding area may experience increased noise level, loading and unloading activities, and restricted access due to safety measures. All road access to PCMS, accommodation areas, and the thrift shop will remain available. However, all road users are advised to exercise caution at all times when using these routes.
If you have any concerns or issues related to the works, including health and safety matters, please contact the DIO(B) Helpdesk as you first point of contact.
- Mon – Sat: 0800 – 1700
- Start mobilisation date: 13 June 2026
- Start construction works: 1 July 2026
- Target completion date: End of Jan 2027
